Issuing of code compliance certificates
The Code Compliance Certificate (CCC) is issued at the end of the building consent process, once the final inspection of the consented work has been passed and any other requirements have been satisfied.
Note: Building Control has 20 working days in which to decide whether to issue a Code Compliance Certificate, however delays in receiving information, or money owed, or the failing of the final inspection, will delay the issuing of the CCC. The CCC should be issued within 20 working days from date of receiving the application for a CCC provided:
- The application for a CCC is received (Form 6).
- The final inspection passed.
- All outstanding fees paid and paperwork has been received.