ENV-2020-CHC-65
Appeal lodged: 8 May 2020
Appeal resolved: 4 August 2022
Status updates:
4 August 2022: Levide Capital Limited – Remaining appeal points withdrawn
21 March 2022: Levide Capital Limited – Withdrawal of appeal points relating to natural hazards
9 August 2021: Levide Capital Limited – Withdrawal of appeal relating to landscape
2 December 2020: Consent order issued resolving appeal points 65.7 and 65.8