Status: Operative
The following operative plan change has been made to the Marlborough Sounds Resource Management Plan and has been incorporated into the Plan.
The RMA requires Councils to place a statement in their Regional Coastal Plans either setting out a coastal occupancy charges regime or to say they will not do so. Variation 2 inserts a new section into the Plan which in essence states that the Council considers the charges are justified, however there are a number of issues which need to be dealt with before a charging regime is introduced.
Key Steps
| Date
|
---|
Operative Date
| 25/08/2011
|
Environment Court Decision
| 29/12/2009
|
Public Notice of Decision
| 18/01/2001
|
Hearing
| 06/11/2000
|
Further Submissions Closed
| 28/09/2000
|
Public Notice of Summary of Submissions
| 31/08/2000
|
Submissions Closed
| 02/06/2000
|
Public Notice of Notification
| 04/05/2000
|