Major utility projects
Council is undertaking some major infrastructure projects. Below are some basic details regarding these projects.
(Please note, this list is of major projects only)
For more detailed information please contact Council directly:
Email mdc@marlborough.govt.nz
Phone (03) 520 7400
Alternatively visit Council offices at:
15 Seymour Street
Blenheim 7201
Blenheim Northwest sewer upgrade | |||
---|---|---|---|
Start | End (approx.) | Contractor | Areas affected |
November 2021 | March 2022 | Schick | Fulton Street |
Budge Street | |||
McLaughlan Street | |||
Corner Nelson/Bomford Streets | |||
SH1 (Budge St intersection) | |||
Bomford St |
Muller road | |||
---|---|---|---|
Start | End (approx.) | Contractor | Areas affected |
12 January 2021 | November 2021 | Fulton Hogan | Muller Road |
(between Redwood and Weld Streets) |
Renwick AC watermain replacement works | |||
---|---|---|---|
Start | End (approx.) | Contractor | Areas affected |
25 January 2021 | Late May 2021 | Crafar Crouch | Northern side of State Highway 6 (SH6) between Pak Lims Road and Uxbridge Street, and 150m along the eastern side of Brook Street, north of the highway. |