Paper building consent applications
The following contains guidelines and tips on applying for a paper version of a building consent:
- Applications must include all of the relevant documentation called for in the application checklist, including the checklist itself, and a fully completed application form.Applications must be fully complete otherwise they are likely to be returned unprocessed
- Make sure the Design Licenced Building Practitioner memorandum is included for all restricted building work
- Do not lodge on memory sticks
- Do not lodge by email
- Paper applications can be provided but will be delayed for scanning and will incur scanning fees
- Only one copy of the documents is required for paper applications
- Applications should be completely on paper
- Ensure plans are the right way up for reading
- Fully complete the application form
- Fully complete the application checklist
- A3 size original sheets for drawing are preferred but large projects will need larger sheets
- Use colour on documents carefully. Colours used must be able to be scanned and printed
- Where colour coding is used for highlighting details or other items (such as truss layouts) please provide those in colour
- With the exception of marquee applications and COA deposits, please do not make payment when submitting a building consent application. The table of building consent fees gives an indication of flat fees before other charges such as the BRANZ and Building levies are added. We will invoice you for the full cost of your building consent once the consent has been issued.
Go to building forms, documents and guidance brochures
Once you have gathered all the necessary information either post the application in, or deliver it in person to our office.
Our postal address is:
Marlborough District Council
PO Box 443
Blenheim 7240
Our Blenheim physical address is:
Marlborough District Council
15 Seymour Street
Blenheim
Our Picton physical address is:
Picton Service Centre and Library
2 Dublin Street
Picton